Skip to content

Concrete Calculator

Calculate how much concrete you need for slabs, columns, and stairs.

Pour dimensions

Updates as you type
Project preset (optional)
Shape
Slab
Length ?
ft
12560100
Width
ft
12560100
Depth ?
in
281624
Adjustments
Waste factor ?
%
0102025
Cost ?
$ / yd³
Display (optional)
Units
Currency

Examples

How It Works

Concrete is a mixture of cement (the binding powder), water, sand, and gravel (aggregate). When combined, these ingredients undergo a chemical reaction called hydration that hardens the mix into a durable, stone-like material used for foundations, driveways, sidewalks, and more.

To estimate how much you need, calculate the volume of the area to be filled. For slabs, it is Length × Width × Depth. For columns, use the cylinder formula π × r² × h. Convert the result to cubic yards (divide cubic feet by 27) or cubic meters for ordering.

Premixed concrete comes in 40-lb, 60-lb, and 80-lb bags, yielding approximately 0.30, 0.45, and 0.60 cubic feet respectively. Always add a 10% waste factor to your calculation — uneven subgrades, spillage, and forms that are not perfectly level mean you will almost always need more than the exact mathematical volume.

Tips & Best Practices

Always order 10% extra: It is better to have leftover concrete than to run short mid-pour. A cold joint from stopping and restarting weakens the slab.
Thickness matters enormously: A 6-inch slab uses 50% more concrete than a 4-inch slab for the same footprint. Measure depth carefully before ordering.
Match thickness to use: Walkways need a minimum of 3.5 inches; driveways and garages need at least 4 inches. Structural slabs may require 6 inches with rebar.
Consider ready-mix delivery: For projects over 1 cubic yard (~45 bags of 80 lb), a ready-mix truck is more cost-effective and produces a more consistent pour.
Curing takes time: Concrete reaches about 70% strength in 7 days and full design strength in 28 days. Keep it moist for the first week for the best result.

Frequently Asked Questions

How much concrete do I need for a slab?

Calculate volume: Length × Width × Thickness (all in the same unit). For example, a 10 ft × 12 ft slab that is 4 inches thick needs 10 × 12 × 0.333 = 40 cubic feet, or about 1.48 cubic yards. Always add 5–10% extra for waste.

Cement is a binding ingredient (powder) made from limestone and clay. Concrete is the finished product made by mixing cement with water, sand, and gravel (aggregate). Cement makes up about 10–15% of the concrete mixture.

Use the cylinder volume formula: V = π × r² × h, where r is the column radius and h is the height. For a 12-inch diameter column that is 8 feet tall: V = 3.14159 × 0.5² × 8 = 6.28 cubic feet.

An 80-lb bag of premixed concrete yields approximately 0.6 cubic feet. Divide your total cubic footage by 0.6 to get the number of bags. For example, 40 cubic feet would need about 67 bags (40 / 0.6 = 66.7).

For walkways and patios, 3.5 to 4 inches is standard. Driveways should be at least 4 inches, and garage floors 4 to 6 inches. Heavy-traffic or load-bearing slabs may need 6 inches or more with reinforcement.

Concrete can be poured in cold weather but requires precautions. Below 40°F (4°C), use heated water and insulating blankets to prevent freezing during the critical first 24-48 hours. Never pour on frozen ground, and avoid pouring below 20°F (−7°C).

Concrete reaches about 70% of its strength in 7 days and full design strength (typically 4,000 psi for residential) in 28 days. You can walk on it after 24-48 hours, drive on it after 7 days, and place heavy loads after 28 days.

For small projects under 1 cubic yard (about 45 80-lb bags), premixed bags are practical. For larger pours, ready-mix truck delivery is more cost-effective, ensures consistent mixing, and allows continuous pouring for a better result.

Rebar (reinforcing bar) is steel placed inside concrete to add tensile strength. It is recommended for driveways, structural slabs, retaining walls, and any concrete over 4 inches thick. For walkways and small patios, wire mesh may be sufficient.

A 5-10% waste factor accounts for spillage, uneven subgrade, forms that are not perfectly level, and concrete left in the mixer or wheelbarrow. Running short mid-pour creates a cold joint that weakens the slab, so it is always better to order slightly more.